NJ Garden Services
Telephone: 0800 075 2080 Mobile Number: 07802 807 114
Quality Garden Maintenance, Construction and Exterior Care. Call us for FREE right now to discuss your needs!
Meet Our Team Garden Gallery Testimonials Diary Bookings
Homepage
About Us
Our Services
Past and Current Projects
Products for Sale
Latest News

Past Projects 2004

Operation "Moresley" - September 2004

This driveway needed deep excavation as the original concrete was very thick.


Operation "Thomas" - September 2004

We're back at the Thomas residence. Front drive this time.


Operation "Hayward" - September 2004

This driveway is the lowest point of the street and so during heavy rain experiences its own little flash flood. The double drive way will have interceptor drainage, however the fall is so steep and so much water comes down at once, we must set the levels to channel the flow away from the buildings.

Sand levels using rods and straight timber A camber is set down the centre line to draw the levels off Sand levels using rods and straight timber


Operation "Atkinso" - August 2004

This is a fairly simple job. Richard is going to slab over the garden but leave a retained wood chip area for a climbing frame.

Day one

The slabs are laid onto compacted M.O.T rock and the play area set between them. The kiddy area is filled with woodchip & the frame cemented in place.


Operation "Folder Frame" - August 2004

This is an Industrial job that a factory has asked us to do for them. Their car park is just bare concrete so we're going to enhance it with a pathway and a raised sleeper border.

The first jobs will be to break out the tarmac and sub materials. Set the lines and install the kerbing. The path is more for cosmetics and to protect the building against parking vehicles than as a functioning path. Below, the kerbs are laid, the base consolidated and now sharp sand is been poured between the edging. The edging was set with precision so the blocks fit perfectly between. The sand is compacted and levelled then the blocks laid. Finally, white car parking bays are painted in.

On the other factory wall we are going to construct a sleeper border with turrets to improve the approach to the reception. The area is excavated then a triple layer of sleepers are fixed together. A membrane is installed to prevent muddy water escaping and a plastic barrier to protect the building. The borders are filled with topsoil and planted out with Hebe, ground Flox and Euonymous.


Operation "Harrison"

Now here is an interesting project. The customer has a large deep pond in the garden and with a large young family are worried about safety. The initial idea was to fill it all in but in the end a decking top not only proved cheaper, but nicer. Also in years to come the pond could be easily repaired. The first job is to clean the pond and remove the fish. Gareth dons some waders and gets muddy. A pump is used to remove the majority of the water. Drainage is made to prevent refilling.

A frame work is constructed using 2 x 6 timbers stretching across the shallow shelves. Strong centre support is put in. The decking profiles are screwed in place and carefully cut around the edges to leave a smooth edged finish.


Operation "Clerke & Wallace"

This next project is a fairly large. The garden is sloped. The customers would like a large two tiered natural stone patio with steps. The higher patio will be retained using old railway sleepers. The patio will also have a circuit of recessed lighting and a Jacuzzi hot tub with power points.

Don't try this at home kids

After marking out the lower area is excavated. In total over 50 tons of soil and clay is removed

Jaccuzzi base

The Jacuzzi base is laid. It needs to hold a lot of water without moving. Lee cuts the retaining sleepers to size. The path edging is laid with coloured mortar.

The sleepers are installed into a deep footing and held in place with cement. The first of two steps are installed. These will be angled in line with the Jacuzzi hot tub.The Jacuzzi is installed and tested.

Flush lighting is installed around the lower patio and wired into a new consumer unit.


Operation "Swan"

This customer has asked for the limited space in his garden to be maximized. We going to deck half the garden with recessed steps into the house and shed. The other half of the garden will be retained and turned into a deep wood chipped play area for the children.



Operation "King" - April 2004

The patio is much lower than the lawn area. We're going to construct a sleeper retainer around the edge of the existing patio that the customer has already built, level the garden area and re turf. First, we must plan how the sleepers will sit together to form a wall and be able to hold back the pressure of the garden over a long period of time.

Richards first job will be to finish digging the footings that were started before. The he will pour in cement to create a solid anchor for the new wall to hold on to.

After all the wood is cut to size it is stacked and secured to the posts set deep into the cement. Cam plates are also screwed to the joins to hold everything together. Steps are cut into the sleeper wall for lawn access. The ground is leveled to the natural fall of the garden. Fresh topsoil is imported, then the turf is laid.


OPERATION "Thomas" - Decking & Play Area

Day one - garden ordinareTim's first job will be to organize the garden a bit. Lift the old patio and dismantle the shed and fence. If all the rubbish can go at once this will help to reduce costs. Then he will set his levels and begin constructing the framework for the new decking. The frame is fixed to the house and posts are installed into the ground at appropriate spaces. Then 2 x 4 lengths of wood will befixed in lines that will support the decking.

Richard has come from the maintenance team to grind out some stumps that are in the way.

A stump grinder.

The decking is complete with a hatch to allow access to the drains underneath.

Play area retainers Panel fence

The play area has now been installed and the shed base and shed erected. Four tons of fresh top soil is imported and evenly spread. When the grounds levels are right the garden is turfed.

Play area retainers Garden extrodinaire Done!

Mrs. Thomas: "We are delighted with the garden. The service we have received has been excellent and the level of workmanship & care taken has been 1st class. It's beautifully finished & we are really looking forward to the summer."


Operation "Burnett" - March 2004

Day one Digging out first patio
First patio finished

The first job is to excavate all the existing crazy paving. After excavation Richard must set his levels so he can determine how much of the sub soil needs to come out to make room for the hard base.

Round top picket2nd patio for shed & pots

Now the ground has been consolidated to the right level the 600mm x 900mm grey slabs can be laid on a sharp mortar bed. Now this is done Mark sets his levels and excavates the patio shed base that will run up one side of the garden and join to the new house patio. Meanwhile Richard begins constructing the new picket fence to keep the customers little dog off the grass. As you can see the rails have been properly azed and inserted into the posts, so no unsightly nails or brackets. The new gate can be attached on Monday after the post cement has gone hard.

Now the second patio is finished Richard can begin leveling the lawn area.The turf is laid - Hey presto!


OPERATION "Beards" Front Driveway - March 2004

Kango drill breaking the old surfaceThis old driveway is just broken bricks, some concrete and a layer of tarmac. The other half is grass and mud. Our first job is to locate all the services that might be running under the ground. Then we begin excavating the top surface. Space is limited so we will stock pile the spoils on the grass area. We know that a certain amount of disruption will occur to the public path so we'll have to replace it. The driveway slopes down to the house where a gully has already been installed. We'll angle the lay of the new driveway so the water quickly drains away from the house.

After the sub soils and old slabs have been dug up a grab lorry arrives to remove the spoils. Now we set the levels and begin to spread type one consolidator. As each layer is spread it is compacted into the clay with a vibrating machine.

Setting the levels Block laying Perfect

Sharp sand is spread over the consolidator and compacted down hard. Then using leveling rods we pull off the surplus to give us a perfect level. The blocks are laid straight down onto the sand in a herring bone fashion. Where the bricks meet obstacles a perfect fit is unlikely so the blocks are cut into the right shape using a diamond blade. Finally a super fine sand is vibrated into the gaps between each block, locking everything in tight.


OPERATION "Copeland" Patio, path and lawn - March 2004

Day one Day one Day one

Richard's first job is to strip out the existing garden. He removes the old crazy paving under the kitchen window and the top layer of old turf and soil. Then he uses existing levels such as the damp course and the drain to determine at what height the new patio will sit. Once he knows this he can peg the ground. By measuring how much space he needs for consolidator, mortar and the slab itself, he can calculate how much of the sub soil is to be removed. Once enough has been dug out his team begins to import the type one consolidator.

The tops of the pegs hammered into the ground at intervals will represent the tops of the final layer. Using a long spirit level he can ensure that once completed the water will run off the patio in the right direction.

Now the levels are correct Richard B & Mark begin to lay the slabs. The circle had an enormous foul drain in the middle so a special lifting tray is inserted into the pattern allowing access to the drain without spoiling the patio. Once the slabs are laid blocks are installed around the edges.

Day one

Finally the turf is laid and the slabs are pointed in.


OPERATION "Jones"

Day one Day one Day one

For more pictures of our previous work visit the gallery.